What does 'scope creep' refer to in project management?

  1. Timely completion of tasks

  2. Uncontrolled changes to the project’s original objectives

  3. Reduction of project costs

  4. Project prioritization

The correct answer is: Uncontrolled changes to the project’s original objectives

Scope creep refers to the phenomenon in project management where there are uncontrolled changes or additions to the project’s original objectives, requirements, or deliverables. This typically occurs when the scope of a project is not properly defined, documented, or controlled. As new requests or changes emerge without proper evaluation, they can significantly disrupt the project’s timeline, budget, and overall goals. When scope creep happens, it can lead to an increase in workload, extend deadlines, and strain resources, ultimately affecting the project’s success. Effective project management involves clear initial definitions of scope and robust change control processes to manage changes systematically, preventing the negative impacts associated with scope creep. This understanding is crucial for maintaining the integrity of the project and ensuring that it meets stakeholder expectations.