West Virginia Contractors License Practice Exam

Disable ads (and more) with a membership for a one time $4.99 payment

Prepare for the West Virginia Contractors License Exam with our comprehensive quiz featuring multiple-choice questions. Each question includes hints and detailed explanations, ensuring you're fully prepared for your licensing test!

Practice this question and more.


After how many days does a permit become invalid if the work authorized does not begin?

  1. 90

  2. 120

  3. 180

  4. 365

The correct answer is: 180

A permit becomes invalid after 180 days if the work authorized does not commence. This time frame is established to ensure that projects proceed in a timely manner, preventing delays that can arise if permits remain valid indefinitely without any progress on the associated work. The 180-day period allows for a reasonable amount of time for the contractor to initiate the work while also providing a mechanism to reassess the need for the permit and the relevance of the project. This time limit promotes efficiency in construction management and keeps the permitting system organized, ensuring that resources are available for active projects instead of being tied up by permits for works that may not happen. The other durations provided do not align with the regulations governing the validity of permits in West Virginia, which is why they do not apply in this context.